Newsletter in August

This week on 9 Apartment Development Elemental Apartments – Upper Floor Plumbing & Electrical Finals in progress. Balcony & Terrace tiling commenced and nearly complete. On Ground Floor we have finished sand float and set to all internal walls. Ceilings are now finished. Window glazing has gone in. We will lock up by end of the week and cabinets installation will follow straight after.

This week on 3 Town Houses in Joondanna: Unit A & B Upper Floor Brickwork completed. Roof Carpenter commencing end of next week.

Unit C : Tiling Completed, Stormwater Completed. Plumbing Finals nearly completed. Shower Screens will be installed by end of this week. Garage Doors are due to be installed at the end of this month. Paving delivery and install to follow.

Units A and B:

This week on 3 Storey Luxury Town Houses in Crawley: Demolition Completed, Earthworks commencing this week.