This week on 9 Apartment Development Elemental Apartments –
Upper Floor - We are about half way complete with Upper Floor Plumbing & Electrical Finals we are expecting this stage to complete in a couple of weeks’ time. Tiler is still working on Balcony & Terrace tiling, rain has slightly impacted on this progress. Common Terrace Patio was installed last week. Ceramic Tiling and Decking will commence shortly.
On Ground Floor - ceilings have been spray painted. All doors are now hung and locked up. Cabinets are now installed in units 1,2,3 & 4, Unit 5 getting installed end of this week. Footings and hardstand to storeroom completed. Ceramic Tiles getting delivered this week in preparation for Tiler commencement.