News

12 May 2017

New Welink Group website is launched!

Our team has been very busy with all our projects as well as servicing our new customers who have just settled in their new homes. Take a look at all our current projects, and if you have any questions about purchasing them or investing into a new project just like […]
15 July 2017

July Updates

Every week we will bring you progress updates on our projects, such as the Elemental Apartments, and our town houses in Joondanna, and our 3 storey townhouses in Crawley, we will also share photos, and all of the important progress information.
1 August 2017

August Updates 1

This week on 9 Apartment Development Elemental Apartments – Upper Floor Plumbing & Electrical Finals in progress. Balcony & Terrace tiling commenced and nearly complete. On Ground Floor we have finished sand float and set to all internal walls. Ceilings are now finished. Window glazing has gone in. We will […]
7 August 2017

August Updates 2

Newsletter Issue No.3 This week on 9 Apartment Development Elemental Apartments – Upper Floor – We are about half way complete with Upper Floor Plumbing & Electrical Finals we are expecting this stage to complete in couple of weeks’ time. Tiler is still working on Balcony & Terrace tiling, rain […]